Project
Leyton Sixth Form College
Location
Leyton, London E10
Products
W35SZ 75mm blade site assembly clip-in louvre screens
Finish
Polyester powder coated 40 microns to RAL7000 Squirrel Grey
Job Type
Supply and installation
Programme
4 weeks manufacturing and 7 days installation
Completed
September 2010
Architect
Archial Architects
Main Contractor
Wates Construction
Sub-Contractor
MARS (Construction)
EDS were awarded the sub-contract to supply and install two louvre screens and two plant room louvres, one with a single access door as a late variation. The W35SZ clip-in blade system was chosen as the simplest system to install as this allowed our fixers to site measure and cut the blade length to suit the actual openings. Installation was completed utilising on-site scaffolding and a MEWP. There were zero Health & Safety issues and our fixers reported minimal disruption.